Gateway West Addition - Storm Sewer Improvements and Lift Station

About this Project

The purpose of the proposed project is to install storm sewer, storm water ponds, and storm sewer lift station to service the Gateway West Addition. The need for the proposed project is warranted by the development of the Gateway West site and the request by the property owner to install the improvements. 

Storm Improvement District No. 4065 will involve the construction of improvements consisting of storm sewer, storm water retention pond, storm sewer lift station, and other miscellaneous installations

Project Schedule

  • Estimated Start Date: September 2018
  • Estimated End Date: October 2018
  • Percent Complete: 0%

Completed Work

  • Ninty percent of topsoil stripped

Current Work

  • Remaining topsoil stripping
  • Site excavation

Upcoming Work

  • Utilities