The Wilds Ninth Addition and Sanitary Lift Station - District No. 1305

About this Project

Infrastructure for The Wilds Ninth Addition and sanitary lift station.

Project Schedule

  • Begin Date: August 2017
  • End Date: September 2018
  • Project Complete: 60%

Road Closures

  • Access roads to development closed

Completed Work

  • Pond
  • Utilities
  • Most of sanitary lift and storm lift station
  • Milestone No. 1 underground and roadway complete

Current Work

  • Dirt work and subgrade preparation
  • Sidewalk
  • Multi-use path
  • Ninth Street paving
  • 3rd-party utilities
  • Curv
  • Streetlights 
  • Mailboxes

Upcoming Work

  • Asphalt paving 
  • Seeding