Eighth Ave. NW and 26th St. NW Paving - District No. 2240

About the Project


This multi-phase project involves utilities, a storm water retention pond, and paving. The project will include paving of Eighth Avenue NW from Ninth Street W. to 26th Street NW, as well as the reconstruction and paving of 26th Street NW from Eighth Avenue W. to First Avenue NW. 

Estimated Construction Costs


  • $3.1 million

Project Schedule


  • Begin Date: October 2017
  • End Date: October 2018
  • Project Complete: 95%

Road Closures


  • Eighth Avenue W. open to local traffic only

Completed Work

  • Main line 100%
  • Driveways 100%
  • Gravel shoulders 90%
  • Dirt work 85%

Current Work


  • Black dirt shoulders
  • Pour street light bases

Upcoming Work

  • Railroad approaches
  • Street signs
  • Seed and mulch
  • BNSF crossing installations (will require 26th Avenue NW closure)