CONSTRUCTION UPDATES
The West Fargo portion of the Main Avenue Reconstruction Project started May 18, 2009. Check out the Maps, Detours, and Projects pages on the website link provided here for information about the Main Avenue Reconstruction Project.
Construction on the 9th Street Continues this week. The pavement markings on 9th Street East from 13th Avenue to 19th Avenue were removed in preparation for Tuesday's lane adjustments and commencement of boulevard removal operations. Lane line markings (yellow and white) are being left in place at this time. On Tuesday, May 26th, northbound traffic will use the easternmost lane, with southbound traffic shifted to the center (double left turn) lane; the westernmost lane will be closed for boulevard removal operations in the west boulevard.