Storm Sewer Lift Station - 4200 Sheyenne St - District No. 4060
75% Complete
Estimated Begin: July 2017Estimated End: November 2017
Last Updated: November 07, 2017

Contractors are building a new storm sewer lift station two block south of 40th Avenue, off of Sheyenne Street. 

Road closures:

  • Sheyenne St. south of 40th Ave. open with 25 mph construction zone, shoulder closed

Completed work:

  • Force main
  • Control structure driveway rough grading east of Sheyenne St.

Upcoming work:

  • Build structure
  • Generator building aggregate import
  • Structure backfill
  • Site grading
  • Interior pipe installation
  • Precast building

Last Updated: November 07, 2017