September 20, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

Sandhills Third Addition - District No. 1301
75% Complete
Estimated Begin: May 2017Estimated End: October 2017
Last Updated: September 20, 2017

Completed work:

  • Sanitary sewer
  • Water
  • Storm sewer
  • Pond
  • 40% road

Upcoming work:

  • Fourth Avenue preparation and paving
  • Remaining paving (expected to be completed by Oct. 5)

Last Updated: September 20, 2017