October 21, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

Oak Ridge 11th Addition - District No. 1303
95% Complete
Estimated Begin: May 2017Estimated End: October 2017
Last Updated: October 16, 2017

Completed work:

  • Streets
  • Grading and pond
  • Fifth Street paved to 32nd Avenue E.

Upcoming work:

  • Seeding
  • Pave 32nd Avenue E. turn lane
  • Curb and gutter
  • Street paving

Last Updated: October 16, 2017

This information can be found at www.westfargond.gov