October 21, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

Eighth Avenue NW and 26th Street NW Paving, Utilities and Pond - District No. 2240 & 1289-II
75% Complete
Estimated Begin: October 2016Estimated End: November 2016
Last Updated: October 16, 2017

This multi-phase project involves utilities, a storm water retention pond, and paving. The project will include paving of Eighth Avenue NW from Ninth Street West to 26th Street NW, as well as the reconstruction and paving of 26th Street NW from Eighth Avenue West to First Avenue NW. 

Road Closures:

  • Eighth Avenue embankment work - expect delays

Completed work:

  • 26th St. NW paving
  • Eighth Avenue concrete returns
  • All underground utilities
  • West Fargo Fifth Addition
  • Embankment work

Upcoming work:

  • Subgrade preparation
  • Fabric fall 2017 followed by gravel
  • Pave Eighth Ave. spring 2018
  • Lift force main and outfall

Last Updated: October 16, 2017

This information can be found at www.westfargond.gov