August 23, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

Eighth Avenue NW and 26th Street NW Paving - District No. 2240
40% Complete
Estimated Begin: October 2016Estimated End: November 2016
Last Updated: August 07, 2017

This multi-phase project involves utilities, a storm water retention pond, and paving. The project will include paving of Eighth Avenue NW from Ninth Street West to 26th Street NW, as well as the reconstruction and paving of 26th Street NW from Eighth Avenue West to First Avenue NW. 

Completed work:

  • Eighth Avenue concrete returns

Upcoming work:

  • Signing
  • Light poles
  • Striping
  • 26th Street final work
  • Gravel fall 2018
  • Pave Eighth Avenue NW spring 2018

Last Updated: August 07, 2017