May 30, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

The Wilds Multi-Use Path Improvements - Horace Diversion to Sheyenne Street
50% Complete
Estimated Begin: May 2017Estimated End: July 2017
Last Updated: May 10, 2017

The final portion of the multi-use path (from Ninth Street W. to 11th Street W. on the south side of the Westport Beach Pond) commenced the week of May 15.

Key Contracting began paving part of the path. If you have private possessions on the city’s pond lot, please move them to your property so they are not damaged during the construction activity.

During the paving operations, there will be times when construction equipment may slow or restrict traffic on Ninth Street W. and 11th Street W.  Prepare to share the road with concrete trucks during the day.

Last Updated: May 22, 2017

This information can be found at www.westfargond.gov