May 30, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

First Avenue E. Reconstruction - Fourth Street E. to Ninth Street E. - Dist. 3001
0% Complete
Estimated Begin: May 2017Estimated End: September 2017
Last Updated: April 27, 2017

This infrastructure replacement project will consist of a full reconstruction of First Avenue E. from Fourth Street E. to Ninth Street E., Fourth Street E. from Main Avenue to First Avenue E., and Fifth Street E. from Main Avenue to First Avenue E. 

We will remove existing water mains, sanitary sewer, streets, and street lights and install new water mains, sanitary sewer, storm sewer, concrete streets, and street lights. Sidewalks will be replaced as needed throughout the project area. 

Beginning Monday, May 15, the contractor will close First Avenue E. from Fourth Street E. to Ninth Street E., as well as Fourth Street E. and Fifth Street E. from Main Avenue to First Avenue E. Remove all parked vehicles and other property on these streets prior to May 15. Access will be provided and maintained by the contractor for businesses and residences that have no other access to their buildings from outside the project area.

Regional traffic will be detoured around the project area as shown in this map


During active construction operations, we ask that you keep vehicles and private property out of the project area and away from the construction site entrances. Thank you for your patience and please drive with care especially when using the detour. 

Last Updated: May 22, 2017

This information can be found at www.westfargond.gov