September 20, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

13th Avenue E. and Ninth Street E. Intersection Improvements - District No. 2243
35% Complete
Estimated Begin: August 2017Estimated End: August 2018
Last Updated: September 11, 2017

The project consists of reconstructing and widening the 13th Avenue East and Ninth Street East intersection to accommodate dual left turn lanes in all directions. The project will also involve the addition of a northbound through lane from 13th Avenue East to Seventh Avenue East, and upgrades to outdated/undersized utilities within project limits to minimize future disruptions.

Detour maps and final layout visuals were available and included in the presentation.

Completed work:

  • Phase 1: Road closures
  • Phase 1: Removals
  • Phase 1: Roadwork/base west of Ninth Street
  • Phase 1: Sanitary sewer force main
  • Phase 1: Water main

Upcoming work:

  • Phase 1: Storm sewer east of Ninth St
  • Phase 1: Ninth Street/13th Ave removals
  • Phase 1: Subgrade east of Ninth Street
  • Phase 1: Subgrade/base east of Ninth Street
  • Phase 1: Pave 13th Ave east and west of Ninth Street

Last Updated: September 11, 2017

This information can be found at www.westfargond.gov