March 28, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

West Fargo Topsoil & Clay swap for Contractors
% Complete
Estimated Begin: March 2016Estimated End: March 2016
Last Updated: March 28, 2016

CLAY AVAILABLE

Improvement District No. 1289-2
8th Ave NW & 26th St NW – Utilities & Pond

Approximate Location = 8th Avenue NW & 26th Street NW
Clay Export = 100,000 cubic yards
Available starting June 2016

Contact: 
Material Owner:
Jeff Eberhardt, Kost Materials 
(701-238-6604)
JEFF@KOSTMATERIALS.COM

Engineer:  
Brandon Reber, Moore Engineering
(701-282-4692)
BReber@mooreengineeringinc.com

City Contractor: 
Dakota Underground Company


4th Street East Clay Pile

Approximate Location = 40th Avenue E & 4th Street E
Clay Export = 8,000 cubic yards
Available starting April 2016

Contact:
Material Owner:  
City of West Fargo

Engineer: 
Matt Welle
(701-282-4692)
MWelle@mooreengineeringinc.com

 

TOPSOIL AVAILABLE

Improvement District No. 1289-2 
8th Ave NW & 26th St NW – Utilities & Pond

Approximate Location = 8th Avenue NW & 26th Street NW
Topsoil Export = 100,000 cubic yards
Available starting June 2016

Contact: 
Material Owner:
Jeff Eberhardt, Kost Materials 
(701-238-6604) 
JEFF@KOSTMATERIALS.COM

Engineer:  
Brandon Reber, Moore Engineering
(701-282-4692) 
BReber@mooreengineeringinc.com

City Contractor:  
Dakota Underground Company

 

CLAY NEEDED

None at this time.

TOPSOIL NEEDED

4th Street East Clay Pile

Approximate Location = 40th Avenue E & 4th Street E

Clay Export = 8,000 CY

Available starting April 2016

 

Contact Info

Owner of Material:  City of West Fargo

Engineer:  Matt Welle (701-282-4692) MWelle@mooreengineeringinc.com

None at this time.
 

 

CLAY NEEDED

Last Updated: August 12, 2016

This information can be found at www.westfargond.gov