Water Tower (Eighth Street W. & Second Avenue W.) – District No. 1260
55% Complete
Estimated Begin: March 2016Estimated End: September 2017
Last Updated: December 13, 2016

This project includes the construction of a new elevated water storage tank on the city lot adjacent to the city’s sanitation facility and deconstructing the existing water tower.

Timeline:

  • Priming/painting tower stem (Current to June 4)
  • Raising tower tank (June 4 to July 9)
  • Priming and painting tank (July 9 to August 9)
  • Adding concrete floor (August 9 to August 16)
  • Sterilizing and testing tank (August 21 to August 28)
  • Demolition of existing tank (Sept. 11 to Sept. 18)

Last Updated: May 22, 2017