July 26, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

Water Tower (Eighth Street W. & Second Avenue W.) – District No. 1260
75% Complete
Estimated Begin: March 2016Estimated End: September 2017
Last Updated: June 29, 2017

This project includes the construction of a new elevated water storage tank on the city lot adjacent to the city’s sanitation facility and deconstructing the existing water tower.

Timeline:

  • Priming/painting tower stem (Current to June 4)
  • Raising tower tank (June 4 to July 9)
  • Priming and painting tank (July 9 to August 9)
  • Adding concrete floor (August 9 to August 16)
  • Sterilizing and testing tank (August 21 to August 28)
  • Demolition of existing tank (Sept. 11 to Sept. 18)

Last Updated: June 29, 2017

This information can be found at www.westfargond.gov