8th Avenue Northwest and 26th Street Northwest (County Road 19 to 26th Street to Main Avenue) – Districts 1289-II & 2240
65% Complete
Estimated Begin: April 2016Estimated End: November 2016
Last Updated: December 13, 2016

26th Street Northwest paving is complete. 8th Avenue Northwest will be addressed in the 2017 construction season.

This project is currently open to traffic with work on hold until the start of the 2017 construction season.

 