May 28, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

Sixth Street W. Realignment and Eighth Avenue W. Reconstruct (Main to 2nd Avenue) – District No. 1273-III
20% Complete
Estimated Begin: April 2016Estimated End: September 2017
Last Updated: November 22, 2016

Sixth Street W. and Sixth Street NW will be realigned on the north and south sides of Main Avenue W. to improve the safety and functionality of the intersection as well as include utility work. Expect lane closures, road closures, detours, and temporary access roads around this project.

Eighth Street W. from Main Avenue to Second Avenue W. will reconstructed and include sanitary sewer and water main improvements. New water mains will also be installed on Second Avenue W. from Sixth Street W. to Eighth Street W.

Update:

Tuesday, May 23, 2017, Dakota Underground will begin removing roadway starting with 6th St W and 2nd Ave W to install new water main. During construction, there will be times when equipment may slow down or restrict traffic to and from the area.  Please be prepared to share the roadway with construction equipment throughout the day.  If there are any issues arising from this construction, please call one of our representatives listed below.  Thank you for your patience and please drive with care through the construction area. 

Moore Engineering, Inc.

Tyler Wentz    On-Site Representative          282-4692 or C205-2858

Ryan Frolek                                                282-4692 or C640-4338

Dakota Underground

Kurt Dwyer      Superintendent                      219-1054

Bob Nelson     Project Manager                     219-1042

Last Updated: May 23, 2017

This information can be found at www.westfargond.gov