Map Use Instructions: To view the map legend, select the ">>" symbol. Zoom in and out by selecting the "+" and "-" symbols. Return to the original extent by selecting the "home" symbol. To change the base map, select the "four-squares" symbol. For project details, select any of the features on the map.

 

 

Current West Fargo Road Construction Projects

65% Complete
Status: 12th Avenue North from Center Street to Ninth Street North closed

Read More


0% Complete
Status: Construction scheduled to begin August 2017.

Read More


75% Complete
Status: Veterans Boulevard right southbound lane will close July 19 to July 26.

Read More


0% Complete
31st Avenue East will close July 24-31 for a manhole repair.

Read More


99% Complete
Status: 32nd Avenue West is currently open to traffic, however occasional lane closures may occur to finish remaining work over the next few weeks.

Read More


99% Complete
Status: Intermittent lane closure may occur as final work is completed.

Read More


40% Complete
Status: Eighth Street West closed from Main Avenue to Second Avenue West to complete underground work.

Read More


50% Complete
Status: Striping to begin August 2017.

Read More


40% Complete
On hold waiting on Eighth Avenue NW permit for work.

Read More


80% Complete
Status: GPS module programming

Read More


30% Complete
Status: Temporary traffic control on Sheyenne Street

Read More


20% Complete
Status: First Avenue East closed from Fourth Street East to Ninth Street East while under construction

Read More


90% Complete
Fourth St. E. and adjoining sidewalks from south of 35th Ave. E to north of the the Splash Pad under repair.

Read More


80% Complete
Status: Crews will begin work May 31, 2017, to replace water main valves in the Meadow Ridge neighborhood.

Read More


10% Complete
Sheyenne Street will be closed from Fourth Avenue West to Fifth Avenue West July 24 to Aug. 3.

Read More


50% Complete
Status: Dakota Underground will begin removing roadway starting with Sixth Street W. and Second Avenue W. to install a new water main.

Read More


75% Complete
Status: Water tank raised Jun 26. No parking on the north side of Second Avenue W. at this time.

Read More


20% Complete
Status: Project started last week of June 2017. Water tower is currently offline but not impacting residents water.

Read More


Future West Fargo Road Construction Projects

0% Complete
The three-year Sheyenne Street corridor reconstruction project is scheduled to begin 2018. This project will ease congestion and safety concerns in West Fargo by redoing the Interstate 94 interchange and adding lanes to Sheyenne Street from 13th to 40th Avenues W.