13th Avenue reconstruction project moving into final phase traffic control

Friday, October 26, contractors for the 13th Avenue Road Reconstruction and Infrastructure Improvement Project will initially shift half of the traffic on the east side of work zone into the final phase of the project.

Motorists traveling westbound on 13th Avenue in Fargo will encounter:
• Traffic will no longer travel side-by-side from west of 45th Street S to east of 16th Street E intersections
• Westbound drivers will shift to the new north side roadway crossing back to be carried side-by-side on the south side of 13th Avenue between 16th Street East and 12th Street East in West Fargo
Eastbound 13th Avenue drivers will remain on the south side of the roadway throughout the entire project limits.

Phase 4 traffic controlWest Fargo north side access change