Highland Meadows First and Second Additions - District No. 1295

About this Project

This project will involve the construction of improvements consisting of sanitary sewer, sanitary sewer televising, water mains, storm sewer, retention pond, asphalt streets, curb and gutter, concrete driveway, sidewalks, curb ramps, street signs, pavement striping, pavement markings, street lights, cluster box units, trees, seeding and mulching, and other miscellaneous installations.

Project Schedule

  • Begin Date: August 2017
  • End Date: June 2018
  • Project complete: 99%

Project Costs

  • Estimated costs: $3.5 million

Completed Work

  • Underground utilities
  • Fabric and gravel
  • Curb and gutter
  • Asphalt paving
  • Path along 21st Avenue
  • Earthwork
  • Sidewalks
  • Seeding
  • Striping
  • Signs

Current Work

  • Diversion rear lot filling

Upcoming Work

  • Rear lot filling and stabilization
  • Culvert abandonment through the levee
  • Waiting on 408 USACE permit